An aerial view of the McNeese Equine Center, which has remained unusable since Hurricane Laura in 2020.Photo courtesy of Porche May Architects
By Dubem Akukwe
The Poke Press

More than six years after Hurricane Laura left the McNeese State University Equine Center unusable, the state has begun reviewing construction bids to demolish and rebuild the facility.

Six contractors submitted bids for the project on Nov. 18, with base bids ranging from approximately $3 million to $4.25 million.
According to preliminary bidding results released by the Louisiana Office of Facility Planning and Control, the bids remain under consideration, with no contract award announced as of Nov. 20.

For agricultural sciences students, the reconstruction would restore hands-on learning opportunities that have been limited since the hurricane.

Darrin Goodwin, McNeese farm and ranch manager, said Hurricane Laura caused a section of the center’s roof to collapse, weakening the surrounding structure. Another section eventually collapsed, and years of exposure to rain contributed to further deterioration. Even moderate winds caused damaged roof components to swing overhead, making it unsafe to continue operations.

“We couldn’t put any livestock in it nor could we have any students in there with it,” Goodwin said.

McNeese maintained two horses after the hurricane, allowing students to continue learning horse handling and preventive care, including vaccinations and deworming. Other aspects of their training, however, could not continue without the facility.

“We were unable to do any stallion collection or breeding of mares,” Goodwin said.

The damage also affected students who owned horses. Before the hurricane, the center offered horse boarding services, allowing McNeese students to keep their horses at the facility for a monthly fee that included stall cleaning.

The closure forced students to find alternative boarding arrangements and resulted in a loss of revenue for the farm.

Rather than repairing the existing structure, the reconstruction project calls for its complete demolition. Goodwin said the new facility will occupy the same footprint as the original building and will include updated electrical and sewer systems.

The project’s architectural firm, Porche May Architects, estimated the base construction cost at approximately $4.46 million. State bidding documents allocate 365 days for construction.

Goodwin said demolition could begin in January 2027 and he hopes the facility will be completed by January 2028. A definitive construction schedule has not been confirmed.

For Goodwin, who has worked at the McNeese farm since 1996, the prospect of rebuilding the facility is exciting.

“When it was built, it was heralded as one of the finest equine centers in the state of Louisiana,” Goodwin said. “And so when they get this new facility built, we’re going to be back with that reputation of having one of the finest facilities in the state of Louisiana.”

Goodwin sees the reconstruction as important not only to McNeese but also to the region’s agricultural community.

“We’ve got horse racing. We’ve got rodeo. We’ve got horse shows. We’ve got judging. I mean, horses are very, very important to Southwest Louisiana,” Goodwin said.

Goodwin said the facility would benefit students interested in veterinary medicine, veterinary technology and horse breeding operations, offering them what he described as “a great hands-on opportunity” to develop the skills needed for their future careers.